Project summary
Major capacity expansion based on proven technology to process growing Talnakh ore volumes and unlock strategic optionality of the South Cluster development project.
Project status
- In 2023, the installation of metal frames of ore dressing units and ore feeders was 90% complete, installation of supports for the process equipment is in progress.
- Installation of reinforced concrete and metal structures is in progress. Foundations for process equipment were built.
- Groundworks at power supply and water recycling facilities were completed.
- Plans for 2024 include completing the installation of metal frames and fences for ore dressing units and ore feeders as well as the bulk of process equipment installation works.
Projected implementation timelineSubject to import substitution of flotation equipment and the target delivery schedule being met.
Commissioning date is to be confirmed as it depends on the projected ore production schedule.